Projects & Milestones

CapNova is currently in the Land & Permitting phase for Copperbelt projects, designed for scalable grid connection and hybrid PV + storage operation.

Priority HV Substations & Corridors (Copperbelt)

Connection points are subject to ZESCO grid impact and feasibility studies. The table below reflects CapNova’s siting preferences and development focus.

Substation / HV Node Area Voltage PV Scale BESS Strategy Priority
Ndola Main / Central Node Ndola 330/220/132 kV 10–100 MW (subject to grid studies) 1–2 hrs (mandatory for higher penetration) Tier 1
Kansenshi Node Ndola 132 kV 10–30 MW 1 hr (optional → recommended) Tier 1 (Phase 1)
Kitwe Main Node Kitwe 330/220/132 kV 10–100 MW (subject to grid studies) 2 hrs (recommended for mining load dynamics) Tier 1
Nkana Nodes Kitwe 132 kV 10–30 MW 1 hr (optional) Tier 2
Lufwanyama Corridor Lufwanyama 132 kV (near HV corridors) 30–100 MW (long-term) 2–4 hrs (strong candidate) Tier 1 (Growth)

Development Timeline

Phase 1 (0–3 months): Land & Permitting
Land identification, municipal engagement, preliminary grid corridor screening.
Phase 2 (3–9 months): Studies & Applications
ESIA, formal grid impact / feasibility study initiation, licensing pathway preparation.
Phase 3 (9–15 months): Structuring & Financing
Offtake discussions, investor/lender engagement, project company structuring.
Phase 4 (15–24 months): EPC & Commissioning
EPC appointment, construction, grid connection, commissioning.

Battery Storage – High-Level Assumptions

Phase 1 (10 MW)

Baseline: 10–20 MWh (1–2 hrs). Final sizing confirmed after grid studies and PPA structure.

Scale-up (30 MW)

Baseline: 60 MWh (2 hrs). Used for peak shifting, voltage support, and curtailment reduction.

Utility-scale (50–100 MW)

Baseline: 100–400 MWh (2–4 hrs). Enables hybrid dispatch and stronger offtake options.